Site Map
 
 

Wodonga Wastewater Treatment Plant

Project Summary

Related Links

 
Project Information Details
Project nameWodonga Wastewater Treatment Plant
Value$32 million (Net Present Value Dec 01)
StatusService Delivery Commenced
Department or agencyNorth East Region Water Authority
Private sector partnerPURAC Pty Ltd now EGL Water Operations Pty Ltd
DescriptionThe Wodonga Wastewater Upgrade Project involves the design, construction and operation of a new wastewater water treatment plant in order to meet environmental performance and effluent re-use requirements.

The upgrade also addresses the need to provide additional wastewater treatment capacity to effectively treat and manage the current and future needs of the Wodonga and outer areas. Domestic and tradewaste customers of the Authority are receiving a better quality service.

In December 2000 North East Region Water Authority (NERWA) contracted PURAC Pty Ltd for the design, building and operation of upgraded wastewater facilities. The contract is for a ten-year term, with two additional terms of five years at the Authority’s discretion. The facility has been operational since July 2003.

A change in control of the private contractor was approved by the Authority in 2005.

This was the first of the Non Metropolitan Urban Water projects to be executed under the Partnerships Victoria policy.
Contact information Jason Mullins
Technology Development Manager
North East Region Water Authority
Phone: 1300 361 622
Email: Jason Mullins
Related informationNorth East Regional Water Authority